Result: The task lists of planned and actual simulation will be shown Further reading: How to Load and Update Schedule in CSV Format - YouTube

To import the actual dates, if you are using MS Project / P6 / PowerProject to create the schedule, you can fill in the columns 'Actual Start' and 'Actual Finish' dates in the scheduling software, export the schedule as an XML file and click the 'Load' button in Fuzor to load the dates using 'Merge by ID'.įurther reading: How to Load and Update schedule from Microsoft Project Primavera P6 Asta Powerproject - YouTubeīut if you are not using these three scheduling software, you would have to create the calendar button in Fuzor to edit the actual start and actual end dates in Fuzor by yourself or use a Excel CSV to edit the dates. Step 1: Load the actual dates to the programme